Electricity grid operator

A grid operator as a walkable model: see how a solar system or heat pump gets connected and when grid planning becomes the bottleneck.

NETZ VELMERAU and all its quantities are invented. Fitted to your grid, the model shows things that appear on no single map today – such as real connection requests per local grid or the loading of your secondary substations.

How does the grid connection of a solar system or heat pump work? The fictional grid operator NETZ VELMERAU shows the process step by step. It connects everyone who asks, keeps the grid running around the clock and rebuilds it at the same time for heat pumps and solar.

The path of a connection request: an installer registers a solar system on the portal, small systems take the simplified route, larger ones go to grid planning for a load flow study, the approval goes out with a timetable, a contractor reinforces the grid where needed, then come meter exchange and register entry. Target in the model: timetable within eight weeks.

In a heat pump boom, grid planners become the bottleneck. Standardised connection packages take work off them, and remote-controlled substations let the control centre switch faster. The page is aimed at management, grid planning, operations, the control centre, metering and regulatory management.

A solar system or heat pump is to be connected

  1. 01

    Installer submits the request: An installer registers a solar system with storage on the portal.

  2. 02

    Grid connection checks the request: Small systems pass the simplified route, larger ones go to load flow.

  3. 03

    Installer submits missing documents: The installer submits the data sheet.

  4. 04

    Grid planning checks compatibility: Grid planning calculates: can the local feeder take the feed-in?

  5. 05

    Approval with timetable: The approval goes out, with timetable and conditions.

  6. 06

    Contractor reinforces the grid: A contractor lays a stronger cable.

  7. 07

    Installer reports completion: The installer builds the system and reports completion.

  8. 08

    Appointment at the customer: An appointment for the meter exchange is arranged.

  9. 09

    Meter exchange: Metering installs a bidirectional meter.

  10. 10

    Register and feed-in payment: Check against the market master data register, payment starts.

  11. 11

    Connected.

How a grid operator can use the model

  • Internal communication

    Control centre, three substations, grid depot, yard and administration on one site. Asset management, operations and connections see how their processes interlock – from request to fault.

    対象Management, communications, all divisions

  • Onboarding

    ‘Who sits where – and reports to whom’ shows locations and responsibilities. New staff see which department takes over when, for a connection request or a cable fault.

    対象New staff in connections, operations and metering

  • Training

    Apprentices trigger ‘Storm’ and follow ‘A medium-voltage cable fails’: alarm, remote switching, fault location, excavation, cable joint, switching back to normal.

    対象Electrical apprentices, work-study students, fault crews

  • Explaining to installers and municipalities

    Installers and local councils see where eight weeks pass and where years pass, as with a new substation. ‘Where the time goes’ makes the difference clear without jargon.

    対象Connections team, customer service, municipalities, installers

  • Strategic overview

    Connection packages, more grid planners, remote-controlled substations and the pace of the smart meter rollout side by side. ‘What each control does’ ranks the levers for faster connections.

    対象Management, regulatory management, asset management

What is shown – why – for whom

表示内容 なぜ 対象
Diagram ‘Where it gets tight’ in a heat pump boom なぜshows grid planning at its limit 対象Management, grid planning
Diagram ‘What each control does’: connection packages, grid planners, remote-controlled substations なぜranks the levers for faster connections 対象Management, regulatory management
Diagram ‘The path across the site’: control centre, substations, depot なぜshows the routes taken during faults 対象Grid operations, control centre
Diagram ‘Where the time goes’: grid connection and substation なぜshows where eight weeks pass and where years pass 対象Installers, municipalities
Diagram ‘Who sits where – and reports to whom’ なぜshows locations and responsibilities 対象Onboarding
Disruption ‘Storm’ with the process ‘A medium-voltage cable fails’ なぜshows fault location and repair under pressure 対象Control centre, crisis team
Process ‘A smart meter is installed’ なぜsets the rollout against the number of fitters 対象Metering

Departments in the model

  • Management

    Leads the grid company – independently of the group's sales.

  • Compliance officer (non-discrimination)

    Ensures all suppliers are treated equally.

  • Asset management

    Owner role: strategy, investment, condition of assets.

  • Grid planning

    Load flow, target grid, (n-1): optimise first, then reinforce, then expand.

  • Regulatory management

    Calculates costs and revenues for the regulator.

  • Grid control centre

    Around the clock: switching, managing outages, planning outages.

  • Fault service

    On standby: drives out, locates, repairs.

  • Maintenance

    Maintains substations, stations and lines.

  • Construction and project delivery

    Builds lines, stations and substations.

  • Grid connection

    Checks requests for solar systems, heat pumps and charging points.

  • Customer service and outage hotline

    Takes reports and informs during outages.

  • Metering

    Installs meters and smart metering systems.

  • Network economics

    Network charges, market communication, feed-in payments.

  • IT and control technology

    Grid control system, geodata, meter data – isolated.

All processes in the model

A solar system or heat pump is to be connected

  1. 01Installer submits the request: An installer registers a solar system with storage on the portal.
  2. 02Grid connection checks the request: Small systems pass the simplified route, larger ones go to load flow.
  3. 03Installer submits missing documents: The installer submits the data sheet.
  4. 04Grid planning checks compatibility: Grid planning calculates: can the local feeder take the feed-in?
  5. 05Approval with timetable: The approval goes out, with timetable and conditions.
  6. 06Contractor reinforces the grid: A contractor lays a stronger cable.
  7. 07Installer reports completion: The installer builds the system and reports completion.
  8. 08Appointment at the customer: An appointment for the meter exchange is arranged.
  9. 09Meter exchange: Metering installs a bidirectional meter.
  10. 10Register and feed-in payment: Check against the market master data register, payment starts.
  11. 11Connected.

A medium-voltage cable fails

  1. 01Protection trips, alarm in the control room: A cable breaks down, protection trips. In the control room the section lights up red.
  2. 02Switch remotely: The control centre isolates the section and resupplies the rest via the ring.
  3. 03Hotline and fault service run in parallel.
  4. 04Outage hotline and outage page: The hotline takes calls, the outage page shows the area.
  5. 05Fault service drives out: The fault service drives to the station.
  6. 06The team is on site.
  7. 07Locating the cable fault: A test van locates the fault in the cable.
  8. 08Emergency generator or temporary fix: An emergency generator supplies the last customers.
  9. 09Contractor digs up: A contractor digs up the street.
  10. 10Fitting a cable joint: Fitters install a cable joint.
  11. 11Switch back to normal state: The control centre switches back to the normal state.
  12. 12Documentation for outage statistics: The fault goes into the statistics.
  13. 13Fixed.

A substation is built

  1. 01Need from the grid expansion plan: Grid planning sees: in the west capacity no longer suffices for heat pumps and charging points.
  2. 02Investment approval: Asset management approves the investment.
  3. 03Assess costs under regulation: Regulatory management assesses: will the costs be recognised?
  4. 04Permit and transformer run in parallel.
  5. 05Permit: The authority approves the substation.
  6. 06Order transformer (lead time): The transformer is ordered.
  7. 07Approved, transformer on its way.
  8. 08Construction: switchgear, protection, cables: Switchgear, protection and cables are built.
  9. 09Control centre plans the outages: The control centre plans which lines are switched off for the tie-in.
  10. 10Commissioning, entry into the control system: The substation goes into operation and appears on the grid display.
  11. 11In operation.

A smart meter is installed

  1. 01Plan installation: Metering plans the installation at a household with a heat pump.
  2. 02Appointment at the customer: Appointment at the customer.
  3. 03Meter exchange: The fitters install meter and gateway.
  4. 04Set up and connect the gateway: The gateway is set up and securely connected.
  5. 05Installed.

What you can change

Controls

  • Connection requests: Subsidy schemes make requests jump.
  • Standardised connection packages: More requests take the simplified route, grid planning is relieved (model assumption).
  • Grid planners: How many load flow studies run at once.
  • Remote-controlled substations: The control centre switches faster (model assumption).
  • Smart meter rollout: More installations tie up the same fitters.

Disruptions

  • Storm: For a day trees fall into lines: twenty times as many faults, location and repair take longer.
  • Excavator damages a cable: For two hours faults pile up in a construction area.
  • Grid control system fails: For two hours the control centre cannot switch remotely.
  • Transformer shortage: For a year transformers take even longer.

What the model gives a grid operator

  • 01

    The bottleneck has a name

    Set connection requests to heat pump boom and the queue at grid planning visibly grows – and a tip at the bottleneck names the control that relieves it.

  • 02

    Operating and expanding at once

    Connection, cable fault, substation build and smart meter installation run in parallel. More installations tie up the same fitters, and the model shows where that gets tight.

  • 03

    Faults with routes

    In a storm, ‘The path across the site’ shows the fault crews moving between control centre, depot and substations.

  • 04

    Supply chains in view

    The ‘Transformer shortage’ disruption stretches the substation build. It shows what a year of extra lead time means for grid expansion.

  • 05

    For committees and big screens

    A browser is enough, and large projections work too – so the model can be shown in council committees, at installer events or in your own lobby.

Basis and limits

Fictional grid operator · model based on researched industry structures · no forecast for real companies

1 case = 1 connection request, 1 fault, 1 substation or 10 smart meters · 1 figure ≈ 25 employees

All volumes, durations, rates and capacities are model assumptions, not values of a real grid operator.

Here the target counts as met when the installer has the timetable; construction and meter exchange follow.

Documented: timetable for connection requests within eight weeks, reporting of interruptions over three minutes, unbundling from sales.

Public sources the model is based on:

  • Energiewirtschaftsgesetz (u. a. §§ 7, 7a, 11, 14a, 14d, 52)
  • Bundesnetzagentur: Monitoringbericht
  • Netzentwicklungsplan Strom (NOVA-Prinzip)
  • Anreizregulierungsverordnung
  • Erneuerbare-Energien-Gesetz § 8

Your grid as a model

Want to show your connection process, your control centre or your grid expansion? We talk about your data and goals. For a first impression you get the password to the simulation from us – just ask.

ご興味があればパスワードをお問い合わせください →

この件について問い合わせる

Minimal Organization: Stromnetzbetreiber

ご入力いただいた情報はこのサイトにのみ送信され、ご返信のためだけに使用されます。

Similar business models

← Minimal Organization

NETZ VELMERAU and all its quantities are invented. Fitted to your grid, the model shows things that appear on no single map today – such as real connection requests per local grid or the loading of your secondary substations.